Summary
Judgment reversed. Sognier, C. J., and McMurray, P. J., concur.
Summary
Judgment reversed. Sognier, C. J., and McMurray, P. J., concur.
Text
Law Offices of John C. Bach, John C. Bach, Gregory W. Glass, Robert J. Hulsey, for appellant.
In July 1989, appellant entered into a contract with the City of Roswell (the "City") for the construction of the Roswell Municipal Center. The contract was a standard American Institute of Architects ("AIA") contract (the "contract"), which required the contractor to incorporate the terms of the contract into each subcontract and to require each subcontractor to be bound by the contract and assume toward the contractor all obligations which the contractor assumed toward the owner. The contract contained a liquidated delay damages paragraph, which provided that if appellant did not complete the construction within 390 days after the commencement date of August 1, 1989, appellant would be liable to the City for liquidated damages in the amount of $300 per day until the construction was complete.
In October 1989, appellant entered into a subcontract with appellee for the supply, fabrication and erection of structural steel needed in the construction project. The subcontract required that appellee perform all work in accordance with the "subcontract documents," which included the Subcontract, the General Conditions of the Subcontract, the Contract, and the Conditions of the Contract (General, Supplementary and other Conditions). The subcontract further provided that all of the subcontract documents were made a part of the subcontract; that appellee was bound by the terms of the general contract; that appellee assumed all obligations, liabilities and responsibilities that the appellant assumed toward the owner; that appellant was entitled to the benefit of all rights and remedies against appellee that the City had against appellant; and that in cases of conflict between the contract and the subcontract, the subcontract would control the relationship between the appellant and appellee. Appellant failed to complete the project within the time period specified in the contract, allegedly due to delays caused by appellee. Appellant subsequently filed an action for damages against appellee, asserting that appellee breached the subcontract by failing to timely fabricate, deliver and erect the structural steel. Appellee moved for partial summary judgment, seeking to limit its liability to $300 per day pursuant to the liquidated damages provision in the contract between appellant and the City. The trial court granted appellee's motion and this appeal followed.
1. In its first enumeration of error, appellant contends that the trial court erred in concluding that appellee, as a subcontractor, could benefit from the liquidated delay damages provision in the contract between appellant and the City. "As a matter of contract law, incorporation by reference is generally effective to accomplish its intended purpose where . . . the provision to which reference is made has a reasonably clear and ascertainable meaning. [Cit.]" Binswanger &c. Co. v. Beers &c. Co.,
2. Appellant also argues that even if the liquidated damages provision were incorporated into the subcontract, the provision is not valid and enforceable under Georgia law. However, in light of our conclusion that the liquidated delay damages provision was ineffective due to its conflict with a provision of the subcontract, it is unnecessary to address this enumeration of error.
Smith & Fleming, Kent P. Smith, Robert O. Fleming, Jr., David A. Rutherford, for appellee.
1992