Summary
Judgment affirmed in part and reversed in part. Deen, P. J., and Sognier, J., concur.
Summary
Judgment affirmed in part and reversed in part. Deen, P. J., and Sognier, J., concur.
Text
Harold B. Yellin, for appellant.
Appellant-contractor filed suit, seeking to perfect and enforce a materialman's lien against the real property of appellee-owner Appellee answered and, in addition, filed a counterclaim wherein it sought to recover liquidated damages for appellant's breach of contract. After a brief period of discovery, appellee moved for summary judgment on its counterclaim and for purposes of its motion only, appellee admitted its liability for the $15,217.02 claimed by appellant as owed to it under the contract. Following a hearing, the trial court granted the motion and entered summary judgment in favor of appellee in the amount of $23,582.98, this figure representing the sum of $38,800 found to be owing to appellee as liquidated damages less the $15,217.02 which was claimed by appellant. Appellant appeals from the trial court's order granting appellee's motion for summary judgment.
1. Appellant enumerates as error the trial court's holding, as a matter of law, that appellee was entitled to liquidated damages for breach of contract.
The record shows that the parties had entered into a construction contract containing an enforceable liquidated damages clause. See OCGA
Viewing the evidence in the light most favorable to appellant, it is clear that the construction contract in question contained a valid liquidated damages clause, that appellant failed to substantially complete its contractual obligations within the time agreed upon by the parties, and that appellant produced no evidence of a contractual defense to appellee's claim for liquidated damages. Accordingly, the trial court did not err in holding, as a matter of law, that appellee was entitled to a recovery of liquidated damages.
2. Appellant enumerates as error the trial court's finding that appellee was entitled to judgment in the amount of $38,800 as liquidated damages.
In its order, the trial court stated that its determination that appellant's substantial completion of the contract work was 388 days late was based upon August 20, 1984 as the contractual due date for substantial completion and an actual substantial completion date of September 12, 1985. There is evidence in the record, however, to authorize a finding that appellee waived the contractual due date of August 20, 1984 and extended it to at least October 5, 1984. "[T]he waiver of contract provisions . . . is a question for the trier of fact when the evidence in that regard is conflicting. [Cit.]" Oxford Motors Co. v. Niblack,
3. The grant of summary judgment in favor of appellee is affirmed as to appellant's contractual liability for liquidated damages. The grant of summary judgment in favor of appellee is reversed as to the award of damages in the amount of $23,582.02.
David H. Johnson, for appellee.
Sponsored links