Summary
Judgment reversed. Felton, C. J., and Eberhardt, J., concur.
Summary
Judgment reversed. Felton, C. J., and Eberhardt, J., concur.
Text
The plaintiff sued the defendant for a sum allegedly due for materials furnished the defendant and used in improvement of the defendant's real estate, and for a special lien on the real estate.
To be entitled to the lien sought the plaintiff was required to prove both the filing for record of his claim of lien within three months after the materials were furnished, and the commencement of an action for recovery of the amount of his claim within 12 months from the time it became due. Ga. L. 1874, p. 45, as amended (Code Ann. 67-2002).
The evidence showed that this plaintiff filed his materialman's lien on November 17, 1965, and that it was recorded within three months from the last delivery of materials included in its claim of lien as required by law. Calhoun Brick Co. v. Pattillo Lumber Co.,
The trial court erred in entering judgment for the defendant.
Howard & Storey, Robert W. Storey, for appellant.
1967